|
Articles
UNDERSTANDING PRELIMINARY NOTICES & STOP NOTICES
By
Karen Theriault, Esq., C.P.M.
There are two means by which a subcontractor, laborer or materialmana
can get paid when the general contractor on a public project doesn’t
pay him - the Stop Notice and the Payment Bond. Each method is used
differently. This article will address Stop Notices only; Payment
Bonds will be addressed in the future. In this article, subcontractor,
laborer and materialman will be jointly referred to as “subcontractor.”
Additionally, the Civil Code will be abbreviated as "CC".
Mechanics’
Lien versus Stop Notice
The Mechanics’ Lien and the Stop Notice are sometimes confused.
Basically, the Mechanics’ Lien is used against private property
and the Stop Notice is used against public property. A Mechanics’
Lien allows an unpaid subcontractor to put a lien against the private
owner’s property to ensure that he gets paid. The Stop Notice
allows the unpaid subcontractor to put what constitutes as a lien
on the contractor’s earnings held by a public agency. Mechanics’
Liens don’t apply to public property because liens against
public property are not allowed.
Once a Stop Notice is
filed it imposes a trust obligation on the public agency (agency),
meaning that the agency must hold the contractor’s earnings
in trust for the subcontractor until the agency can release it by
one of the means allowed by law, as explained below.b The contractor
may file claims against both the Stop Notice and the Payment Bond
at the same time. A stop notice must be preceded by a preliminary
20-day notice. A stop notice that is served after the money has
been disbursed by the public agency has no effect.
Stop Notice
versus Payment Bond
The main difference between the Stop Notice and the Payment Bond
is with which entity the claim is filed. The subcontractor files
both when the general contractor does not pay him. However, Stop
Notices are filed with the public agency and they impose a duty
on the agency to take certain steps to enable the unpaid subcontractor
to get paid. Claims against Payment Bonds are filed with the surety
(the bonding company) and they do not affect the agency. The agency’s
only responsibility towards the Payment Bond is to require the general
contractor to submit one when required by law to do so. Payment
Bonds are required on all public works projects in excess of twenty-five
thousand dollars ($25,000) as discussed below. Agencies will sometimes
require the successful contractor to file a Payment Bond even when
the agency is not required by law to request one.
The Preliminary
Notice
A sub-contractor does not have a right to file a Stop Notice unless
she first files Preliminary Notice. The Preliminary Notice says
to the public agency "Heads up! If I don't get paid by the
general contractor I will be filing a Stop Notice." If the
agency receives a Stop Notice it should immediately look to see
if the person filing it has already filed a Preliminary Notice.
Basically, the subcontractor files a Preliminary Notice merely to
protect her right to later file a Stop Notice in the event the general
contractor fails to pay her. Therefore, an agency may receive many
Preliminary Notices on a job but if the general contractor pays
the sub-contractors that filed the Preliminary Notices the agency
will never receive Stop Notices from those subs.
Author's Note: The Stop
Notice Process is technical and riddled with deadlines. Additionally,
the law changes from time to time so be sure to consult with your
agency's counsel before taking any action.
The Preliminary
20-Day Notice Requirement
Who Must
Give a Preliminary Notice?
A Stop Notice subcontractorc who had no direct contractual relationship
with the contractor must give a preliminary 20-day notice in order
to maintain his right to file a Stop Notice later in the event that
he is not paid by the general contractor.
To Whom
Must the Preliminary Notice be Given?
This notice must be given both to the contractor and to the public
agency.d
When Must
the Preliminary Notice be Given?
Traditionally, a subcontractor on a public works project who fails
to give a preliminary 20-day loses all rights to proceed with a
subsequent Stop Notice claim. However, Legislation in 1995 changed
this requirement. Now, subcontractors may give their preliminary
20-day notice anytime within twenty days of the date or dates the
subcontractors furnished labor or material. However, notice is only
effective for labor, service or materials furnished within the 20-day
period prior to the service of the notice. A subcontractor forfeits
his right to recover for anything supplied or furnished prior to
the 20-day period preceding the notice.
How Must
the Preliminary Notice be Given?
Notice must be given either personally or by first-class mail, registered
mail or certified mail, postage prepaid in an envelope addressed
to the contractor and the Public agency concerned and not later
than 20 days after the subcontractor has furnished labor, services,
equipment, or materials to the job site.
What Must
the Preliminary Notice Contain?
Notice must state with substantial accuracy a general description
of the labor, service, equipment or materials furnished, or to be
furnished, and the name of the party to whom the same was or will
be furnished.
What is
the Penalty for Failure to Give Preliminary 20-Day Notice?
Failure to give the preliminary 20-day notice results in complete
loss of Stop Notice rights and where the cost of the work exceeds
$400, failure of any licensed contractor to give this notice will
subject him to disciplinary action by the Registrar of Contractors.e
Right of
Public Agency (Owner) to Demand Stop Notice
The Public agency has the right to demand service of stop notices
and any potential claimant failing to serve a stop notice in response
forfeits all rights, CC§3158. This procedure enables the Public
agency to determine the existence of all potential lien claims on
the project. Some owners follow the practice of demanding stop notices
under CC§3158 immediately on receiving a preliminary 20-day
notice. However this practice creates problems for a claimant who
has not yet completed furnishing labor, or materials, and is not
yet owed any money. Civil Code §3110 uses the past tense in
describing entitlement to rights under the mechanics' lien law,
and a claimant should be entitled to file a stop notice after he
or she has furnished labor or materials and money is owed. (The
interaction of CC§§3110 and 3158 on this issue is unclear,
however, and claimants' attorneys should be cautious when advising
their clients how to proceed.)
Time Line
- The public agency collects the Payment Bond before the general
contractor starts work.
- The subcontractor must file a Preliminary Notice with the Public
Agency and the general contractor within twenty days of the date
or dates that he furnished labor or material. He must file the
Preliminary Notice to protect his right to file a Stop Notice
in the event the general contractor does not pay him for the labor
and or material that he furnished.
- If the general contractor does not pay the subcontractor, he
must serve the public agency with a Stop Notice within 30 days
after the recording of a notice of completion. If no notice of
completion is recorded, the Stop Notice must be served within
90 days after completion or cessation of work on the project.
The Stop Notice on public work does not have to be accompanied
by a bond (as is required on private works.)
- The public agency must give the subcontractor notice of the
expiration of the Stop Notice period within 10 days after the
filing of a notice of completion or after the cessation of labor
has been deemed a completion or after the acceptance of completion,
whichever is later. (The subcontractor must pay the public agency
$2.00 at the time of the filing of the Stop Notice in order to
receive this notice.)
- If the subcontractor files an action to enforce the Stop Notice
(generally a law suit), the suit may be filed at any time after
10 days, but no later than 90 days following the expiration of
the Stop Notice period.
What are the Public
Agency’s Duties?
- The public agency has specific duties with regards to Stop
Notices. The public agency is required to withhold the amounts
claimed in a Stop Notice until and unless:
- it accepts a release bond from the contractor (see below);
or
- the contractor files an affidavit for summary release and
the subcontractor fails to file a counter affidavit within
the time specified by the Public agency; or
- the subcontractor fails to commence a Stop Notice action
within the time allowed. The time allowed is as follows:
- The Stop Notice must be served on the public agency
within 30 days after the recording of a notice of completion
(or notice of acceptance) or notice of cessation, if such
notice is recorded. If no notice of completion is recorded,
the Stop Notice must be service within 90 days after completion
or cessation.
- The filing of a law suit to enforce the Stop Notice
may be filed at any time after 10 days, but no later than
90 days following the expiration of the Stop Notice period;
or
- the action to enforce a Stop Notice is dismissed; or
- judgment is rendered (by a court) against the subcontractor
in a Stop Notice action or in a summary declaration of rights
proceeding.f
- The public agency must give the subcontractor notice of the
expiration of the Stop Notice period within 10 days after the
filing of a notice of completion or after the cessation of labor
has been deemed a completion or after the acceptance of completion,
whichever is later.g
- The subcontractor must pay the public entity $2.00 at the
time of the filing of the Stop Notice in order to receive
this notice.
- Service must be by personal service or registered or certified
mail.
This notice warns the subcontractor as to the last date on
which an action can be filed on the Stop Notice. Even if the
subcontractor has filed the action, notice may be important
because the subcontractor cannot bring the action to trial
nor have judgment entered until the expiration of the 90-day
period following the expiration of the period within which
Stop Notices must be filed. The filing of an action to enforce
the Stop Notice may be filed at any time after 10 days, but
no later than 90 days following the expiration of the Stop
Notice period.
- Once the subcontractor has given timely Preliminary Notice
and has filed a Stop Notice with the public agency during the
allowable time, the Public agency is under a mandatory duty to
withhold funds.
Disputed Stop Notices
If the Stop Notice is disputed, the original contractor or subcontractor
may either file a release bond (at the discretion of the public
entity) or the original contractor may utilize the summary proceeding
procedure or both.
- Release Bond:
Civil Code Section 3196 provides that the Public agency may permit
the original contractor to file with the public agency a corporate
surety bond in an amount equal to 125% of the claim stated in
the Stop Notice. The existence of this bond protects the subcontractor
in that it substitutes for the funds withheld.
- Summary Proceedings:
If the original contractor disputes the Stop Notice subcontractor’s
right to have the public agency withhold money from the general
contractor, he may institute summary proceedings to resolve the
withhold issue (see Civil Code Section 3197.)
What
are the Subcontractor’s Duties?
-
The Stop Notice shall be filed with the public agency.h
-
No Stop Notice will be invalid by reason of any defect in form
if it is sufficient to substantially inform the public agency
of the information required.
-
A Stop Notice may be served by personal service, registered or
certified mail.
-
To be effective the Stop Notice must be served within 30 days
after the recording of a notice of completion. If no notice of
completion is recorded, the Stop Notice must be service within
90 days after completion.
-
Stop Notices may be filed prior to the date that payment is due
to the general contractor.
a A “materialman” is a person who supplies
materials.
b California Mechanics’ Lien Law and Construction Industry
Practice, 6th Edition, by Matthew E. Marsh and Harry M. Marsh, Parker
Publications, P.O. Box 9040, Carlsbad, CA 92018-9040
c other than a laborer
for wages (a laborer working directly for the general contractor)
or an express trust fund
d Civil Code 3098.
e Civil Code Section 3098(b)
f Civil Code Sections 3196-3203
g Civil Code Section 3185
h It shall be filed in the office of the controller, auditor, or
other public disbursing officer whose duty it is to make payments
under the provisions of the contract, or with the commissioners,
managers, trustees, officers, board of supervisors, board of trustees,
common council, or other body by whom the contract was awarded.
Copyright
© 2004 by Karen Theriault, Esq., C.P.M.
|